Electrical energy and cost for the Mirror Fusion Test Facility [electronic resource]

An operational scenario for the Mirror Fusion Test Facility has been developed based on System Requirements, experience with existing systems, and discussions with project engineers and designers who are responsible for the systems. This scenario was used to project the electrical energy required fo...

Full description

Saved in:
Bibliographic Details
Online Access: Online Access
Corporate Author: Lawrence Livermore National Laboratory (Researcher)
Format: Government Document Electronic eBook
Language:English
Published: Livermore, Calif : Oak Ridge, Tenn. : Lawrence Livermore National Laboratory ; distributed by the Office of Scientific and Technical Information, U.S. Dept. of Energy, 1983.
Subjects:

MARC

LEADER 00000nam a22000003u 4500
001 b7307624
003 CoU
005 20110301000000.0
006 m o d f
007 cr |||||||||||
008 130208e19830201cau ot f0|||||eng|d
035 |a (TOE)ost6163914 
035 |a (TOE)6163914 
040 |a TOE  |c TOE 
049 |a GDWR 
072 7 |a 70  |2 edbsc 
086 0 |a E 1.99:ucid-19739 
086 0 |a E 1.99:ucid-19739 
088 |a ucid-19739 
245 0 0 |a Electrical energy and cost for the Mirror Fusion Test Facility  |h [electronic resource] 
260 |a Livermore, Calif :  |b Lawrence Livermore National Laboratory ;  |a Oak Ridge, Tenn. :  |b distributed by the Office of Scientific and Technical Information, U.S. Dept. of Energy,  |c 1983. 
300 |a Pages: 57 :  |b digital, PDF file. 
336 |a text  |b txt  |2 rdacontent. 
337 |a computer  |b c  |2 rdamedia. 
338 |a online resource  |b cr  |2 rdacarrier. 
500 |a Published through the Information Bridge: DOE Scientific and Technical Information. 
500 |a 02/01/1983. 
500 |a "ucid-19739" 
500 |a "DE83010982" 
500 |a Pence, G.A. 
520 3 |a An operational scenario for the Mirror Fusion Test Facility has been developed based on System Requirements, experience with existing systems, and discussions with project engineers and designers who are responsible for the systems. This scenario was used to project the electrical energy required for the facility. Each system is listed showing the equipment that has been considered, the amount of power requested, and in most cases, the power that it is now connected. 
536 |b W-7405-ENG-48. 
650 7 |a Thermonuclear Power Plants.  |2 local. 
650 7 |a Mftf Devices.  |2 local. 
650 7 |a Open Plasma Devices.  |2 local. 
650 7 |a Power Generation.  |2 local. 
650 7 |a Public Utilities.  |2 local. 
650 7 |a Magnetic Mirrors.  |2 local. 
650 7 |a Cost.  |2 local. 
650 7 |a Electricity.  |2 local. 
650 7 |a Thermonuclear Devices.  |2 local. 
650 7 |a Power Plants.  |2 local. 
650 7 |a Electric Utilities.  |2 local. 
650 7 |a Plasma Physics And Fusion Technology.  |2 edbsc. 
710 2 |a Lawrence Livermore National Laboratory.  |4 res. 
710 1 |a United States.  |b Department of Energy.  |b Office of Scientific and Technical Information.  |4 dst. 
856 4 0 |u http://www.osti.gov/servlets/purl/6163914-K9mnGG/  |z Online Access 
907 |a .b73076247  |b 03-07-23  |c 02-11-13 
998 |a web  |b 02-11-13  |c f  |d m   |e p  |f eng  |g cau  |h 0  |i 1 
956 |a Information bridge 
999 f f |i 2b1e4935-5e8d-5a49-868e-03f2769ed3c8  |s 7f6581d1-153c-5999-802d-dd8d7cff4ba8 
952 f f |p Can circulate  |a University of Colorado Boulder  |b Online  |c Online  |d Online  |e E 1.99:ucid-19739  |h Superintendent of Documents classification  |i web  |n 1